La Línea Vertical Perú has carried out an important work of security accompaniment for a Romero Group contractor during the installation of thermo-acoustic roofs in a new building.
The work consisted of installing more than 1,300m2 of roofing and all its auxiliary elements, such as gutters and ridge tiles. The project was planned to be carried out in 12 days, but the work took longer and was finally completed in 25 days.



A team of more than 14 technicians took part in this project, who received specific training beforehand from the rescuers of La Línea Vertical. Specifically, our professionals provided training to the technicians who were going to carry out the installation, showing them how to manoeuvre and work on the roof. They also practised the use of the temporary lifelines installed on the deck.
The work was carried out in a satisfactory manner, with a notable absence of incidents.